961 - NEWCASTLE INNER CITY BYPASS

Hornery, Sonia to the Minister for Transport and Infrastructure representing the Minister for Roads, Maritime and Freight, and Vice-President of the Executive Council
  1. What is the current status of the Newcastle Inner City Bypass Stage 5 plans?
  2. Will Stage 5 plans be put on public display in the near future?
    1. If so, when?
  3. What is the expected commencement date of works on Stage 5?
  4. What is the expected completion time for Stage 5?
Answer -

I am advised:

Planning is well under way for the 3.4 kilometer final section of Newcastle Inner City bypass between Rankin Park and Jesmond.

In the 2014-15 Budget, the Government committed $150 million from Restart NSW towards construction of the $280 million stage five section from Rankin Park to Jesmond. $4 million has been allocated in the 2015-16 Budget to continue planning for stage five.

Roads and Maritime Services expects to display the refined concept design for community and stakeholder comment later in 2015, with construction to start in 2017 and open to traffic by the end of 2019.


Question asked on 11 August 2015 (session 56-1) and printed in Questions & Answers Paper No. 20
Answer received on 15 September 2015 and printed in Questions & Answers Paper No. 29